Payment Issue in Malaysian Construction Industry: Contractors’ Perspective
DOI:
https://doi.org/10.11113/jt.v70.2804Keywords:
Payment, contract, dispute, delay, adjudication, arbitrationAbstract
This paper research entitled “Payment Issue in Malaysian Construction Industry by Contractor†intends to investigate the causes of late and non-payment in the Malaysian construction industry. Payment problems are old age issues that permeate the Malaysian construction industry. So often, contractors and parties in the construction industry complain either not getting paid or payments have been unduly delayed by the employer. A preliminary study was undertaken of 100 samples of contractors. The findings of the research shows that the potential major causes of late and non-payment are local attitude, delay in certification by consultant and paymaster's poor financial management. Based on the factor analysis findings, there are three factors that should be taken care which are under factor management and documentation, communication and contract, and culture and attitude. Findings of this study may assist the government and relevant parties in addressing problems associated to late and non-payment in an effective and timely manner to create a win-win situation for all parties in the Malaysian construction industry. The findings will be used as a platform in establishing the payment scenario in Malaysian construction industry prior to Construction Industry Payment Adjudication Act (CIPAA).
References
KLRCA. 2012. Arbitration Rules 2012. Kuala Lumpur Regional Centre for Arbitration.
Azman, M. N. A., Dzulkalnine, N., Hamid, Z. A., Kamar, K. A. M., & Nawi, M. N. M. 2013, May 2013. Payment Scenario in the Malaysian Construction Industry Prior to CIPAA. Paper presented at the CIB World Building Congress 2013, Brisbane, Australia.
Memon, A. H., Rahman, I. A., Abdullah, M. R., & Azis, A. A. A. 2011. Assessing the Effects of Construction Delays on MARA Large Projects. International Journal on Advance Science, Engineering and Information Technology. 1: 624–629.
Abdul-Rahman, H., Takim, R., & Min, W. S. 2009. Financial Related Causes Contributing to Project Delay. Journal of Retail & Leisure Property. 8: 225–238.
Artidi, D. and Chotibhongs, R. 2005. Issues in Subcontracting Practice. Journal of Construction Engineering and Management ACSE. 8: 666–876.
Hasmori, M. F., Ismail, I., & Said, I. (2012, 12-13 March 2012). Issues of Late and Non-Payment among Contractors in Malaysia. Paper presented at the 3rd International Conference on Business and Economic Research, Bandung, Indonesia.
Rahman, H. A., & Ye, K. M. 2010. Risk of Late Payment in the Malaysian Construction Industry. World Academy of Science, Engineering & Technology. 41: 538–546.
OGC. 2007. Guide to Best 'Fair Payment' Practices.
Mohamad, M. I., Nekooie, M. A., & Kamaruddin, N. C. 2012. The Adequacy of Contractual Provisions in Managing Construction Failure in Malaysia. European Journal of Business Management. 4: 22–38.
Masons, P. 2011. The Construction Act and Its Amendment–Payment Issues. Out-Law.com.
Odeyinka, H. A., & Kaka, A. 2005. An Evaluation of Contractor's Satisfaction with Payment Terms Influencing Construction Cash Flow. Journal of Financial Management of Property and Construction. 10: 171–180.
Reeves, K. 2003. Pay Up (Vol. 1/2003): JUBM Construction News and Views.
Judi, S. S., & Rashid, R. A. 2010. Contractor’s Right of Action for Late or Non-Payment by the Employer. Journal of Surveying, Construction @ Propoerty. 1: 65–95.
Assaf, S. A., & Al-Hejji, S. 2006. Cause of Delay in Large Construction Projects. International Journal of Project Management. 24: 349–357.
Greenwood, D. 2001. Subcontract Procurement: are Relationships Changing? Construction Management and Economics. 19: 5–7.
Fong, L. C. 2005. The Malaysian Construction Industry- Present Dilemmas of Unpaid Contractors. Master Builders. 4: 80–82.
Supardi, A, & Adnan, H. 2011. Security of Payment in Malaysian Construction Industry: Sub-contract ‘Payment upon Certification’ Cases. Paper presented at the International Conference on Construction and Project Management, Singapore.
Zakaria, Z., Ismail, S., & Md. Yusof, A. 2013. Fundamental Variables of Final Account Closing Success in Construction Projects in Malaysia. International Journal of Social, Human Science and Engineering. 7: 1–6.
Toor, S. U. R., & Ogunlana, S. O. 2008. Problems Causing Delays in Major Construction Projects in Thailand. Construction Management and Economics. 26: 395–408.
Zakaria, Z., Ismail, S., & Md. Yusof, A. 2012. Cause and Impact of Dispute and Delay the Closing of Final Account in Malaysia Construction Industry. Journal of Southeast Asian Research. 2012: 1–12.
Kikwasi, G. J. 2012. Causes and Effects of Delays and Disruptions in Construction Projects in Tanzania. Australasian Journal of Construction Economics and Building, Conference Series. 1: 52–59.
Downloads
Published
Issue
Section
License
Copyright of articles that appear in Jurnal Teknologi belongs exclusively to Penerbit Universiti Teknologi Malaysia (Penerbit UTM Press). This copyright covers the rights to reproduce the article, including reprints, electronic reproductions, or any other reproductions of similar nature.