LATE PAYMENT PRACTICES IN THE MALAYSIAN CONSTRUCTION INDUSTRY

Authors

  • Mohd Khairul Anas Mohd Badroldin Department of Structures and Materials, Faculty of Civil Engineering, University Teknologi Malaysia, 81310 Johor Bahru, Johor, Malaysia.
  • Abdul Rahim Abdul Hamid Department of Structures and Materials, Faculty of Civil Engineering, University Teknologi Malaysia, 81310 Johor Bahru, Johor, Malaysia.
  • Syazwani Abdul Raman Department of Structures and Materials, Faculty of Civil Engineering, University Teknologi Malaysia, 81310 Johor Bahru, Johor, Malaysia.
  • Rozana Zakaria Department of Structures and Materials, Faculty of Civil Engineering, University Teknologi Malaysia, 81310 Johor Bahru, Johor, Malaysia.
  • Saeed Reza Mohandes Department of Structures and Materials, Faculty of Civil Engineering, University Teknologi Malaysia, 81310 Johor Bahru, Johor, Malaysia.

DOI:

https://doi.org/10.11113/mjce.v28.16005

Keywords:

Late payment, claim, work progress, impact, construction industry

Abstract

Factors that influence contractors „cash flow are the frequency of payment, delay, profit margin, retention fund, payment term to the supplier and subcontractor, advanced payment and others. Late payment from the client has become a habit in the construction industry and this practice had caused many implications such as bankruptcy, the higher contract sum due to higher risk, uncomfortable relationship between the payer and payee, disturbance of supply chain and others. The aim of this paper is to examine the late payment practices in the Malaysian construction industry. Thirty seven (37) sets of questionnaire had been collected among the Grade G7 contractors and subcontractors in the state of Selangor based on convenience sampling. The collected data were analysed by using frequency distribution and relative important index (RII). The Data then was tabulated and illustrated in the form of charts. The results of the study show that the late payment is one of the most critical problems in the Malaysian construction industry. The majority of the contractor experienced late payment quite frequently and even beyond the stipulated contract term. The top three impacts of the late payment problems are the negative chain effect on other parties, delay in project completion and lead to bankruptcy or liquidation

References

Abdul-Rahman, H., Takim, R. and Min, W. J (2009). Financial-related causes contributing to

project delays, Retail Leisure Property, 8: 225. doi:10.1057/rlp.2009.11

Azhan, S. (2004). The Effects of Delays in Construction Industry. Master Degree Project Report,

UniversitiTeknologi Malaysia, Skudai.

Chin, L.S. and Hamid, A.R.A. (2015). The Practice of Time Management on Construction

Project. Procedia Engineering, 125: 32–39. doi:10.1016/j.proeng.2015.11.006.

CIDB (2012). Construction Industry Development Board, Enactment of the Construction

Industry Payment and Adjudication Act or CIPAA for Malaysia.Seminar on Legal Reforms

in the Malaysian Construction Industry.Kuala Lumpur: CIDB.

Experian (2003). Late Payment November 2003. London. Retrieved from

website:http://www.experian.com/blogs/ask-experian/category/credit-advice/reportadvice/report-details/late-payment/.

Halim, M.S., Jaafar, M., Osman, O. and Akbar, S. (2010), The Contracting firm‟s failure and

financial related factors: a case study of Malaysian contracting firms,International Research

Journal of Finance and Economics, 2 (3):108-116.

Hamid, A.R.A, Botiti, D.M.C and Mohandes, S.R. (2015). Managing the Delayed Completion on

Construction Project.Journal of Advanced Research in Business and Management Studies.

(1):14-24.

Haseeb, M., Lu X., Dyian M., and Rabbani, W. (2011). Problems of Projects and Effects of

Delays in the Construction Industry. Australian Journal of Business and Management

Research, 1(5): 41-50.

Hasmori, M.F., Ismail, I. and Said, I. (2012) Issues of Late and Non-Payment Among

Contractors in Malaysia. 3rd International Conference on Business and Economic Research

Proceeding, 12-13 March 2012, Golden Flower Hotel, Bandung, Indonesia.

Holt, G. D., Olomolaiye, P.O. and Harris, F.C. (1996). Tendering Procedures, Contractual

Arrangements and Latham-The Contractors' View.Engineering, Construction and

Architectural Management, 3(1&2):97-115. DOI: http://dx.doi.org/10.1108/eb021025.

Judi, S. S. and Abdul Rashid, R. (2010). Contractor‟s Right of Action for Late or Non-Payment

by the Employer.Journal of Surveying, Construction & Property, 1(1):65-95.

Latham, M. (1993), Trust and Money – Interim Report of the Joint Government Industry Review

of Procurement Arrangements in the UK Construction Industry, London: HMSO.

Latham, M. (1994) Constructing the Team, Joint Review of Procurement and Contractual

Arrangements in the United Kingdom Construction Industry, Final Report, HMSO.

Liang S.Y., Putuhena F.J. , Ling L.P. & Baharun A. (2014) “Towards Implementation and

Achievement of Construction and Environmental Quality in The Malaysian Construction

Industryâ€, Malaysia Journal of Civil Engineering, 26(1) pp. 99-114

MBAM (2005). Master Builders Association Malaysia, Quarterly Survey on Progress Payment

Issue in the Construction Industry – 3rd Quarter 2005. Kuala Lumpur: Master Builder.