Abstract

Exploration well GH-02 will be drilled directionally at an inclination of 44º and a target of 5920 ft MD or 4840 ft TVD. So that the drilling process can be safe, the rig capacity must be determined optimally so that it is not over capacity which causes higher rig rental costs and also low capacity which causes disruption of the drilling process. The main components that influence the calculation of the horsepower required by the rig are the hoisting system, the rotary system, and the circulation system. The amount of horsepower required in the hoisting system is influenced by the lifting velocity, the hook load and the efficiency factor. While the rotary system is influenced by the amount of rpm and the target depth. Circulation system is influenced by the pump flow rate and pressure loss along the circulation system. The total horsepower required can be calculated by adding up the horsepower from the hoisting system, rotary system, circulation system, plus the safety factor of 100-250 HP for rigs with more than 1000 horsepower. The drilling time is designed optimally so that not much time is wasted which can cause the drilling costs to increase expensive. The amount of the rig rental cost is obtained from the rig rental cost per day with the planned drilling time. The results of the case study calculations show that the rig capacity is 1500 horsepower, drilling is carried out for 22 days and the cost of renting the rig is 660000 USD

References

Cherutich, Stephen K., 2009 "Rig Selection and Comparison of Top Drive and Rotary Table Drive System for Cost Effective Drilling Projects in Kenya," Report Number 8, UNU-GTP, Orkustofnun, Reykjavík, Iceland

Ndirangu, Eustace G., 2000 “Selection of A Future Geothermal Drilling Rig For Kenya,” Report Number 14, UNU-GTP, Orkustofnun, Reykjavík, Iceland

Okwiri, Lilian A., 2013."Geothermal Drilling Time Analysis: A Case Study Of Menengai And Hengill," Report Number 25, UNU-GTP, Orkustofnun, Reykjavík, Iceland

Kipsang, Carolyn., 2013 “Cost Model for Geothermal Wells,” Report Number 11, UNU-GTP, Orkustofnun, Reykjavík, Iceland

Thorhallsson, Sverrir and Sveinbjornsson, Bjorn M., 2012 “Geothermal Drilling Cost and Drilling Effectiveness,” Presented at Short Course On Geothermal Development And Geothermal Wells, UNU-GTP and LaGeo, Santa Tevla, El Salvador,

Gul, Sercan., and Aslanoglu, Volkan., 2018 “Drilling and Well Completion Cos Analysis of Geothermal Wells in Turkey”, Proceedings, 43rd Workshop on Geothermal Reservoir Engineering, Stanford, California, USA,

Adams, Neal J., 1985. "Driling Engineering A Complete Well Planning Approach," 1st Edition PennWell Publishing Company, Tulsa, Oklahoma, USA

Rabia, H., 2001 “Well Engineering and Construction,” Entrac Consulting,

Sitorus, K., Nanlohy, F. and Simajuntak, J., 2001 “Drilling Activity in the Mataloko Geothermal Field, Ngada-NTT, Flores-Indonesia”, Proceeding of the 5th INAGA. Annual Scientific Conference and Exhibitions, Yogyakarta, Indonesia

Ngugi, Paul K., 2008 "Geothermal Well Drilling," Presented at Short Course III on Exploration for Geothermal Resources, UNU-GTP and KenGen, Lake Naivasha, Kenya

Khaemba, Abraham W., and Onchiri, Dennis M., 2016"BHA and Drilling Parameters Design For Deviation Control in Directional Wells-Menengai Experience," Proceeding of the 6th African Geothermal Conferece. Addis Ababa, Ethiopia

Hole, Hagen., 2006“ Directional Drilling of Geothermal Wells,” UNU-GTP, National Energy Authority, Okustofnum, Iceland,

Razak, Nendra M., and Rini, Dyah, and Herianto 2020, “Rig Capacity Planning for PT Mantap Siak (MS) and PT Mantap Kampar (MK) Drilling Campaign,” Paper presented at 2nd International Conference on Earth Science, Mineral, and Energy AIP Conference Proceedings, AIP Publishing, doi : hhtps://doi.org/10.1063/5.0006798

APMI Document, “Decree No 061/SK/APMI/02/2018”. APMI. 2018

T.Herianto, 2008. Estimate Rig Capacity Design For Oil and Gas Drilling Operation, Earth Science Nasional Preceding, Yogyakarta

Downloads

Published

2022-02-28

Issue

Section

Articles

How to Cite

ESTIMATE RIG CAPACITY AND RENTAL COST IN DRILLING OPERATION GH-02 WELL EXPLORATION MATALOKO GEOTHERMAL FIELDRATION GH-02 WELL EXPLORATION MATALOKO GEOTHERMAL FIELD. (2022). ASEAN Engineering Journal, 12(1), 75-82. https://doi.org/10.11113/aej.v12.16727