LEAN IMPACT ON MANUFACTURING PRODUCTIVITY: A CASE STUDY OF INDUSTRIALIZED BUILDING SYSTEM (IBS) MANUFACTURING FACTORY

Authors

  • Muhammad Harith Zainal Abidin Department of Mechanical and Manufacturing Engineering, UPM, 43400, Serdang, Malaysia https://orcid.org/0000-0002-3373-0611
  • Zulkiflle Leman Department of Mechanical and Manufacturing Engineering, UPM, 43400, Serdang, Malaysia https://orcid.org/0000-0002-3273-6675
  • Zainal Abidin Mohd Yusof Department of Chemical Engineering Technology, Universiti Kuala Lumpur MICET, Lot 1988, Bandar Vendor 70800, Alor Gajah Melaka, Malaysia
  • Amjad Khalili Article history Received 28 December 2021 Received in revised form 18 March 2022 Accepted 18 Mar

DOI:

https://doi.org/10.11113/jurnalteknologi.v84.18156

Keywords:

Lean manufacturing, value stream mapping, benchmarking, manufacturing productivity

Abstract

According to a recent study, Lean Manufacturing (LM) adoption in the Malaysian Industrialized Building System (IBS) industry is still low due to a variety of barriers, including misconceptions, the use of modular coordination, a lack of detailed guidelines and the Lean culture is still in its infancy in the field of IBS. This paper examines the impact of Lean Manufacturing approaches towards the manufacturing productivity in Malaysian IBS Manufacturing factory. An integration method of Value Stream Mapping (VSM) and benchmarking for measuring manufacturing plant performance and total productivity is offered. The company was able to improve its performance in each manufacturing department by implementing a lean approach. After improvement, the overall manufacturing plant performance index increased from 0.75 to 0.78, resulting in a 4.00 percent increase in total factor productivity. The proposed improvement features extracted from essential lean methods such as JIT, TPM and CI can be used by practitioners to increase the level of Lean Manufacturing implementation in Malaysian manufacturing firms.

Author Biography

  • Zulkiflle Leman, Department of Mechanical and Manufacturing Engineering, UPM, 43400, Serdang, Malaysia
    1. Department of Mechanical and Manufacturing Engineering, UPM, 43400, Serdang, Malaysia
    2. Associate Professor 

References

Solla, M., Ismail, L. H., & Yunus, R. 2016. Investigation on the Potential of Integrating BIM into Green Building Assessment Tools. ARPN Journal of Engineering and Applied Sciences. 11(4): 2412-2418.

Ariffin, S. T., Yunus, R., Mohammad, H., & Yaman, S. K. 2017. A Preliminary Review on Economies of Scale (EOS) Towards Industrialized Building System (IBS) Manufacturer. MATEC Web of Conferences EDP Sciences.103: 03008.

Koskela, L. J., & Howell, G. 2002. The Underlying Theory of Project Management is Obsolete. Proceedings of the PMI Research Conference PMI. 293-302.

Meiling, J., Backlund, F. and Johnsson, H. 2012. Managing for Continuous Improvement in Off‐site Construction: Evaluation of Lean Management Principles. Engineering, Construction and Architectural Management. 19(2): 141-158. https://doi.org/10.1108/09699981211206089.

Azadeh, A., Zarrin, M., Abdollahi, M., Noury, S., & Farahmand, S. 2015. Leanness Assessment and Optimization by Fuzzy Cognitive Map and Multivariate Analysis. Expert Systems with Applications. 42(15-16): 6050-6064. https://doi.org/10.1016/j.eswa.2015.04.007.

Sanders, A., Elangeswaran, C., & Wulfsberg, J. P. 2016. Industry 4.0 Implies Lean Manufacturing: Research Activities in Industry 4.0 Function as Enablers for Lean Manufacturing. Journal of Industrial Engineering and Management (JIEM). 9(3): 811-833. http://dx.doi.org/10.3926/jiem.1940.

Haq, A. N., & Boddu, V. 2015. An Integrated Fuzzy QFD and TOPSIS Approach to Enhance Leanness in Supply Chain. International Journal of Business Performance and Supply Chain Modelling. 7(2): 171-188.

Lucherini, F., & Rapaccini, M. 2017. Exploring the Impact of Lean Manufacturing on Flexibility in SMEs. Journal of Industrial Engineering and Management (JIEM). 10(5): 919-945. http://dx.doi.org/10.3926/jiem.2119.

Dhiravidamani, P., Ramkumar, A. S., Ponnambalam, S. G., & Subramanian, N. 2018. Implementation of Lean Manufacturing and Lean Audit System in an Auto Parts Manufacturing Industry–An Industrial Case Study. International Journal of Computer Integrated Manufacturing. 31(6): 579-594. https://doi.org/10.1080/0951192X.2017.1356473.

Alawag, A. M. M., Alaloul, W. S., Liew, M. S., Al-Bared, M. A. M., Zawawi, N. A. W. A., & Ammad, S. 2021. The Implementation of the Industrialized Building System in the Malaysian Construction Industry—A Comprehensive Review. Proceedings of the 3rd International Conference on Separation Technology Springer, Singapore. 3-16. https://doi.org/10.1007/978-981-16-0742-4_1.

Zairul, M. 2021. A Thematic Review on Industrialised Building System (IBS) Publications from 2015-2019: Analysis of Patterns and Trends for Future Studies of IBS in Malaysia. Pertanika Journal of Social Sciences and Humanities. 29(1): 635-652.

Laureto, J. J., Dessiatoun, S. V., Ohadi, M. M., & Pearce, J. M. 2016. Open Source Laser Polymer Welding System: Design and Characterization of Linear Low-density Polyethylene Multilayer Welds. Machines. 4(3): 14. https://doi.org/10.3390/machines4030014.

Du, C., Dai, Y., Guan, C., & Hu, H. 2021. High Efficiency Removal of Single Point Diamond Turning Marks on Aluminum Surface by Combination of Ion Beam Sputtering and Smoothing Polishing. Optics Express. 29(3): 3738-3753. https://doi.org/10.1364/OE.417537.

Li, Q., Pan, C., Jiao, Y., & Hu, K. 2018. Research on PCBN Tool Dry Cutting GCr15. Machines. 6(3): 28. https://doi.org/10.3390/machines6030028.

Karkalos, N. E., Karmiris-Obratański, P., Kurpiel, S., Zagórski, K., & Markopoulos, A. P. 2021. Investigation on the Surface Quality Obtained during Trochoidal Milling of 6082 Aluminum Alloy. Machines. 9(4): 75. https://doi.org/10.3390/machines9040075.

Mihalache, A. M., Nagîț, G., Slătineanu, L., Hrițuc, A., Markopoulos, A., & Dodun, O. (2021). Evaluation of the Ability to Accurately Produce Angular Details by 3D Printing of Plastic Parts. Machines, 9(8): 150. https://doi.org/10.3390/machines9080150.

Gallo, P., Romano, R., & Belardi, E. 2021. Smart Green Prefabrication: Sustainability Performances of Industrialized Building Technologies. Sustainability. 13(9): 4701. https://doi.org/10.3390/su13094701.

Ayob, A., Razali, N., Hassan, Z., Rahim, M. A., & bin Mohd Zahid, M. Z. A. 2021. Carbon Footprint Assessment of Hostel Building Construction Using the Industrialized Building System in Pauh Putra, Perlis. Journal of Physics: Conference Series IOP Publishing. 1793(1): 012035. https://doi.org/10.1017/CB0978110415324.004.

Noor, S. R. M., Yunus, R., Abdullah, A. H., Nagapan, S., Syahir, S. M., & Mazlan, S. 2018. Insights into the Adoption of Lean Management in Industrialised Building System (IBS) Implementation: The Drivers and Challenges. International Journal of Engineering & Technology. 7(3.23): 22-31.

Yunus, R., Suratkon, A., Wimala, M., Hamid, H. A., & Noor, S. R. M. 2016. Motivational Factors on Adopting Modular Coordination Concept in Industrialized Building System (IBS). MATEC Web of Conferences EDP Sciences. 47: 04017. https://doi.org/10.1051/matecconf/20164704017.

Yunus, R., Noor, S. R. M., Nagapan, S., Hamid, A. R. A., Tajudin, S. A. A., & Jusof, S. R. M. 2017. Critical Success Factors for Lean Thinking in the Application of Industrialised Building System (IBS). IOP Conference Series: Materials Science and Engineering IOP Publishing. 226(1): 012045. https://doi.org/10.1088/1757-899X/226/1/012045.

Berawi, M. A., Berawi, A. R. B., & Hadwart, K. A. 2012. Managing Construction Logistics Management: Findings from Construction Contractors and Industrialized Building System (IBS) Manufacturers. African Journal of Business Management. 6(5): 1932-1944. https://doi.org/10.5897/AJBM11.2047.

Mohd Nawi, M. N., Lee, A., Noor, M., Azman, A., & Mohamad Kamar, K. A. 2014. Fragmentation Issue in Malaysian Industrialised Building System (IBS) Projects. Journal of Engineering Science and Technology. 9(1): 97-106. http://repo.uum.edu.my/id/eprint/10608.

Rahman, A. B. A., & Omar, W. 2006. Issues and Challenges in the Implementation of Industrialised Building Systems in Malaysia. Proceedings of the 6th Asia-Pacific Structural Engineering and Construction Conference (APSEC 2006). 5-6. http://www.theedgeproperty.com.my/content/ibs-adoption-malaysia-remains-low-cidb.

Tagliari, L. D., Pandolfo, A., & Zeilmann, R. P. 2020. Developing a Specific Structured Procedure to Assess Sustainability Performance in Manufacturing Processes. Journal of Cleaner Production. 269: 122404. https://doi.org/10.1016/j.jclepro.2020.122404.

Thomas, H. R., Maloney, W. F., Horner, R. M. W., Smith, G. R., Handa, V. K., & Sanders, S. R. 1990. Modeling Construction Labor Productivity. Journal of Construction Engineering and Management. 116(4): 705-726.

Thomas, H. R., & Završki, I. 1999. Construction Baseline Productivity: Theory and Practice. Journal of Construction Engineering and Management. 125(5): 295-303. https://ascelibrary.org/doi/abs/10.1061/(ASCE)0733-9364(1999)125:5(295).

Nawi, M. N. M., Lee, A., Kamar, K. A. M., & Hamid, Z. A. 2012. Critical Success Factors for Improving Team Integration in Industrialised Building System (IBS) Construction Projects: The Malaysian case. Malaysian Construction Research Journal. 10(1): 45-63. http://repo.uum.edu.my/id/eprint/17894.

Singh, R. K., Modgil, S. and Tiwari, A. A. 2019. Identification and Evaluation of Determinants of Sustainable Manufacturing: A Case of Indian Cement Manufacturing. Measuring Business Excellence. 23(1): 24-40. https://doi.org/10.1108/MBE-08-2018-0056.

Habidin, N. F., Hashim, S., Fuzi, N. M. and Salleh, M. I. 2018. Total Productive Maintenance, Kaizen Event, and Performance. International Journal of Quality & Reliability Management. 35(9): 1853-1867. https://doi.org/10.1108/IJQRM-11-2017-0234.

Sharma, A. K., Joshi, A., & Jurwall, V. 2020. Performance Measurement Metrics in TPM: A Contextual View to Training and Development. Materials Today: Proceedings. 28: 2476-2480. https://doi.org/10.1016/j.matpr.2020.04.796.

Hamja, A., Maalouf, M., & Hasle, P. 2019. The Effect of Lean on Occupational Health and Safety and Productivity In The Garment Industry–A Literature Review. Production & Manufacturing Research. 7(1): 316-334. https://doi.org/10.1080/21693277.2019.1620652.

Sabry Shaaban, M. and H. Awni, A. 2014. Critical Success Factors for Total Productive Manufacturing (TPM) Deployment at Egyptian FMCG Companies. Journal of Manufacturing Technology Management. 25(3): 393-414. https://doi.org/10.1108/JMTM-09-2012-0088.

Aboelmaged, M. 2018. The Drivers of Sustainable Manufacturing Practices in Egyptian SMEs and their Impact on Competitive Capabilities: A PLS-SEM Model. Journal of Cleaner Production. 175: 207-221. https://doi.org/10.1016/j.jclepro.2017.12.053.

Orji, I. J., & Wei, S. 2014. A Decision Support Tool for Sustainable Supplier Selection in Manufacturing Firms. Journal of Industrial Engineering and Management (JIEM). 7(5): 1293-1315. http://dx.doi.org/10.3926/jiem.1203.

Perini, S., Luglietti, R., Margoudi, M., Oliveira, M., & Taisch, M. 2017. Training Advanced Skills for Sustainable Manufacturing: A Digital Serious Game. Procedia Manufacturing. 11: 1536-1543. https://doi.org/10.1016/j.promfg.2017.07.286.

Hussein, S. G., Al-Shammari, M. A., Takhakh, A. M., & Al-Waily, M. 2020. Effect of Heat Treatment on Mechanical and Vibration Properties for 6061 and 2024 Aluminum Alloys. Journal of Mechanical Engineering Research and Developments. 43(01): 48-66.

Winterkorn, R., Pittner, A., & Rethmeier, M. 2021. Wire Arc Additive Manufacturing with Novel Al-Mg-Si Filler Wire—Assessment of Weld Quality and Mechanical Properties. Metals. 11(8): 1243. https://doi.org/10.3390/met11081243.

Suryaprakash, M., Prabha, M. G., Yuvaraja, M., & Revanth, R. R. 2021. Improvement of Overall Equipment Effectiveness of Machining Centre Using Tpm. Materials Today: Proceedings. 46: 9348-9353. https://doi.org/10.1016/j.matpr.2020.02.820.

Yang, J., Xie, H., Yu, G., & Liu, M. 2021. Achieving a Just–in–time Supply Chain: The Role of Supply Chain Intelligence. International Journal of Production Economics. 231: 107878. https://doi.org/10.1016/j.ijpe.2020.107878.

Pérez-Gosende, P., Mula, J., & Díaz-Madroñero, M. 2020. Overview of Dynamic Facility Layout Planning as a Sustainability Strategy. Sustainability. 12(19): 8277. https://doi.org/10.3390/su12198277.

Nozari, H., Fallah, M., & Szmelter-Jarosz, A. 2021. A Conceptual Framework of Green Smart IoT-based Supply Chain Management. International Journal of Research in Industrial Engineering.10(1): 22-34.

Downloads

Published

2022-05-30

Issue

Section

Science and Engineering

How to Cite

LEAN IMPACT ON MANUFACTURING PRODUCTIVITY: A CASE STUDY OF INDUSTRIALIZED BUILDING SYSTEM (IBS) MANUFACTURING FACTORY. (2022). Jurnal Teknologi (Sciences & Engineering), 84(4), 65-77. https://doi.org/10.11113/jurnalteknologi.v84.18156