THE RISK RATING OF DELAY RISK FACTOR OF ROAD CONSTRUCTION PROJECT IN PAPUA
DOI:
https://doi.org/10.11113/mjce.v29.15608Keywords:
Road construction, risk rating, delay risk factorAbstract
Papua Province is one of the target areas of national development program in Indonesia. The development program covers the acceleration of road construction. The issue regarding this acceleration is the frequent occurrence of delay in the road construction project in Papua. This research delivers the risk rating of delay risk factors of road construction project in Papua. The delay risk factors are grouped into project factors; owner; contractor; consultant; design; materials; equipment; labor; external factor; finance and economic; and finance and political factors. Nine risks with high categories are generated from the risk assessment, which are (1) Social and Cultural Effect; (2) Physical factors in the working field; (3) Traffic obstruction within and around the project area; (4) Public security; (5) Ineffective delay penalties; (6) A poor relationship with local communities; (7) Lack of productivity; (8) Change-order by owner during construction; and (9) Delay in revising designs by owner. The risks with high category should be mitigated by performing several methods since the early stage of the project. The methods include conducting public discussion, performing comprehensive field survey, performing adequate cost estimation, preparing a sufficient contract, and executing a proper site supervision system.References
Alwi, S., Hampson, K., and Mohamed, S. (2002). “Waste in Indonesian Construction Projects.†Creating a Sustainable Construction Industry in Developing Countries, Proceedings of the 1st International Conferences of CIB W107, (2002), South Africa, 305-315.
Assaf, S.A. and Al-Hejji (2006). “Cause of delay in large construction projects.â€International Journal of Project Management, 24(1), 349-357.
Aziz, R.F. (2013). “Ranking of delay factors in construction projects after Egyptian Revolution.â€Alexandria Engineering Journal, 52(3),387-406.
Aziz, R.F., and Abdel-Hakam, A.A.(2016). “Exploring delay causes of road construction projects in Egypt.â€Alexandria Engineering Journal,. 55(1), 1515-1539.
BPS Provinsi Papua. (2015) Rencana Strategis BPS Provinsi Papua 2015 – 2019. Jayapura: BPS Provinsi Papua.
Connor, D.M. (1976). “Citizen inputs to public works projects.†Engineering Issues, 102(1), 29-39.
Gündüz, M., Nielsen, Y., and Özdemir, M. (2013). “Quantification of delay factors using the relative importance index method for construction projects in Turkey.†Journal of Management in Engineering, 29(2), 133-139.
Jahanger, Q.K. (2013). “Important Causes of Delay in Construction Projects in Baghdad City.â€Australian Journal of Basic and Applied Sciences, 7(4), 14-23.
Kaliba, C., Muya, M., and Mumba, K. (2009). “Cost Escalation and Schedule Delays in road Construction Project in Zambia.†International Journal of Project Management, 27(1), 522-531.
Kendrick, T. (2015). “Identifying Project Scope Risk.â€Identifying and Managing Project Risk, 3rd ed., (3), Amacom, New York, 49-70.
Koehn, E., and Winkleman, L.C. (1981). “Public Reaction to Construction Project.†Journal of the Construction Division, 107(2), 209-217.
Marzouk, M.M. and El-Rasas, T.I. (2014). “Analyzing delay causes in Egyptian construction projects.†Journal of Advanced Research, 5(1), 49-55.
Ministry of Public Works and Housing Republic of Indonesia. (2015) Strategic Plan of Ministry of Public Works and Housing Republic of Indonesia 2015 – 2019. Jakarta: Ministry of Public Works and Housing Republic of Indonesia.
Othman, A.A.E. (2005). “Value and risk management protocol for dynamic brief development in construction.†Emirates Journal for Engineering Research, 10(2), 23-36.
Perera, B., Dhanasinghe, I., and Rameezdeen, R. (2009). “Risk Management in Road Construction : The Case of Sri Langka.†International Journal of Strategic Property Management,13(2), 87-102.
Project Management Institute (2013). “Project Risk Management.†A Guide to The Project Management Body of Knowledge, 5th ed., (11), Project Management Institute, Newtown Square, 313-346.
Sjawal, M., and Wiguna, I.P.A. (2009). “Analisis risiko terhadap biaya pelaksanaan pada proyek konstruksi konstruksi jembatan di Provinsi Papua.†Seminar Nasional Aplikasi Teknologi Prasarana Wilayah. Proceedings of National Conference of ITS, (2009), Surabaya, 557-564.
Unas, S.E., Hasyim, M.H., Negara, K.P. (2014) Antisipasi Keterlambatan Proyek Menggunakan Metode What If Diterapkan pada Microsoft Project. Jurnal Rekayasa Sipil, 8 (3): 192 – 197