LABOUR PRODUCTIVITY OF BLOCKWORK ACTIVITY IN SELECTED PUBLIC BUILDING PROJECTS IN AKWA IBOM STATE, NIGERIA
DOI:
https://doi.org/10.11113/mjce.v27.15909Keywords:
Blockwork activity, construction, labour productivity, variability, work studyAbstract
This study aims at establishing labour productivity norm and assignable causes of variability of construction labour productivity for blockwork activity. A descriptive survey research design approach was adopted. Data were collected on a gang comprising of a bricklayer and mate for 30 working days using project work study manual as the research instrument. Descriptive statistics and statistical control charts were the tools used for analysis. The results show that the average and baseline construction labour productivities of blockwork activity are 0.83m2/hr and 1.07m2/hr respectively. Variability in construction labour productivity of blockwork activity was observed to be due to assignable causes of weather condition and delay in supply of materials. It is recommended that ample consideration should be given to the effect of adverse weather condition during labour cost estimation by taking into cognisance the period of execution of the project. Similarly, adequate planning of construction resources will help in enhancing labour productivity on public building projectsReferences
Attar, A.A., Gupta, A.K. and Desai, D.B. (2012) A study of various factors affecting labour productivity and methods to improve it. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), 1(3): 11-14.
Atser, J.(2008). Analysis of Spatial Patterns of Social Infrastructure in Rural Areas of Akwa Ibom State, Nigeria, Ph.D. Thesis, Department of Geography and Regional Planning,
University of Uyo, Uyo, 238 pp.
Ayandele, J.O. (1996) Evaluation of Factors that Affect Labour Productivity of some Selected Building Trades on Nigerian Construction Sites. Ph.D. Thesis, Department of Building,
University of Lagos, Nigeria, 317 pp.
Bertelsen, S. (2004) Lean construction where are we and how to proceed? Lean Construction Journal, 1(1): 46-69.
Central Public Works Department (CPWD) (2009) CPWD Specifications, Vol. 2. Nirman
Bhawan, New Delhi: Director General of Works, pp. 1032.
Chitkara, K. K. (2006) Construction Project Management. Planning, Scheduling and Controlling. (11th ed.), New Delhi: Tata McGrawhill Publishing Company Limited, 771 pp.
Choy, E. and Ruwanpura, J.Y. (2006) Predicting construction productivity using situation-based
simulation models, Canadian Journal of Civil Engineering 33: doi: 10.1139/L06-088:
-1600.
Christian, J., and Hachey, D. (1995) Effects of delay times on production rates in Construction, Journal of Construction Engineering and Management, ASCE, 121(1): 20-26.
Dawood, N.N., Hobbs, B. and Fanning, A. (1999) Standardization of Brickwork Construction: Process Identification. In: Hughes, W. (Ed.), 15th Annual ARCOM Conference, 15 – 17 September 1999, Liverpool John Moores University. Association of Researchers in
Construction Management, 2: 395-404.
EPSRC (2004) Managing Changes in Construction Projects. An Industrial Research Report Funded by Engineering and Physical Sciences Research Council (EPSRC). Available at:
http://www.bne.uwe.ac.uk/cprc/publications/mcd.pdf, 4 June, 2014.
Gulezian, R., and Samelian, F. (2003) “Baseline determination in construction labor productivityloss
claimsâ€, Journal of Management and Engineering, 19(4): 160-165.
Hanna, A. S., Chang, C., Sullivan, K. T., and Lackney, J. A. (2008) Impact of shift work on labour productivity for labour intensive contractor, Journal of Construction Engineering
and Management, 138(3): 197-204.
Harris, R. and McCaffer, R. (2006) Modern Construction Management. West Sussex: WileyBlackwell, 680 pp.
Hill, S.E. and Schvaneveldt, S.J. (2011) Using statistical process control charts to identify the steroids era in major league baseball: an educational exercise, Journal of Statistics Education, 19(1): 1-19.
Hopp, W. and Spearman, M. (1996) Factory Physics: Foundations of Manufacturing Management, Boston: Irwin/McGraw-Hill, 668 pp.
Huang, A. L., Chapman, R. E. and Butry, D. T. (2009) Metrics and Tools for Measuring Construction Productivity: Technical and Empirical Considerations. Gaithersburg,
Maryland: U.S. Department of Commerce National Institute of Standards and Technology, 179 pp.
Ibbs, W., Nguyen, L.D. and Lee, S. (2007) Quantified impacts of project change, Journal of
Professional Issues in Engineering Education and Practice, 133(1): 45-52.
Idiake, J.E. and Bala, K. (2012) Improving labour productivity in masonry work in Nigeria: the application of lean management techniques. In: Laryea, S., Agyepong, S.A., Leiringer, R.
and Hughes, W. (Eds) Proceedings of 4th West Africa Built Environment Research (WABER) Conference, 24-26 July 2012, Abuja, Nigeria: 677-686.
Jongeling, R. (2006) A Process Model for Work-flow Management in Construction. Ph.D. Thesis, Department of Civil and Environmental Engineering, Lulea University of Technology, 61 pp.
Lucey, T. (2002) Quantitative Techniques. 6th ed., Bedford Row, London: BookPower, p 91.
McTague, B. and Jergeas, G. (2002) Productivity Improvements on Alberta Major Construction Projects: Phase I – Back to Basics. Construction Productivity Improvement Report/Project
Evaluation Tool. Available at:
http://www.assembly.ab.ca/lao/library/egovdocs/alet/2002/154992.pdf, 19 June, 2014, 127 pp.
Mojaheed, S. (2005) A Project Improvement System for Effective Management of Construction Projects. Ph.D. Thesis, Agricultural and Mechanical College, Louisiana State University, 218 pp
Noor, I. (1992) A Study of the Variability of Labour Productivity in Building Trades. Ph.D.
Thesis, Department of Civil Engineering of the University of Dundee, 268 pp.
Odesola, I.A. (2012) Construction Labour Productivity of Masonry Operations in South-South of Nigeria. Ph.D. Thesis, Department of Building, University of Uyo, Nigeria, 487 pp.
Odesola, I.A. and Idoro, G.I. (2014) Construction Labour Productivity as a Correlate of Project Performance: An Empirical Evidence for Blockwork Activity. In: Proceedings of CIB
Conference 2014, 376-387.
Olomolaiye P.O. and Ogunlana S.O. (1989) An evaluation of production outputs in key building trades in Nigeria, Construction Management and Economics, 7: 75-86.
Otti, V.I. (2012) Engineering implication for millennium development goals in revamping and sustaining Nigeria economy, International Journal of Engineering Research and Applications (IJERA), 2(2):1373-1377.
Park, H., Thomas, S.R. and Tucker, R.L. (2005) Benchmarking of construction productivity, Journal of Construction Engineering and Management, 131(7): 772-778.
Smith, M.A. (2000) Control Charts. Available at: http://carbon.ucdenver.edu/~mas/ coursemtls/ccharts.pdf, 4 September, 2014, 18 pp.
Song, L. and AbouRizk, S. M. (2008) Measuring and modelling labour productivity using historical data, Journal of Construction Engineering and Management, 134(10): 786-794.
Sweis, R.J., Sweis, G.J., Abu Hammad, A.A. and Abu Rumman, M.A. (2009) Modelling the variability of labour productivity in masonry construction, Jordan Journal of Civil
Engineering, 3(3): 197-212.
Thomas, H. R. and Sanvido, V. E. (2000) quantification of losses caused by labor inefficiencies: where is the elusive measured mile? Journal of Construction Law and Business, 1(3):1-14.
Thomas, H. R., and ZavrÅ¡ki, I. (1999) “Construction baseline productivity: theory and practiceâ€, Journal of Construction Engineering and Management, 125(5): 295-303.
Thomas, H.R., Sanders, S.R. and Horner, R.M.W. (1989) Procedures Manual for Collecting Productivity and Related Data on Labour-intensive Activities on Commercial Projects:
Final Report, Issue 9004. Pennsylvania: Pennsylvania Transportation Institute, 93 pp.
Walker, D.H.T. (1995) An investigation into construction time performance, Construction Management and Economics, 13: 263-274.