COST-BENEFIT ANALYSIS OF USING BIM COMPARED TO TRADITIONAL METHODS IN IRAQ'S PUBLIC CONSTRUCTION PROJECTS
DOI:
https://doi.org/10.11113/aej.v13.18982Keywords:
BIM, Construction projects, Benefit-cost, Traditional methodsAbstract
The construction procurement process generates significant cost-related issues, such as project delivery delays, budget overruns, and poor quality. Public projects were suffering from bureaucracy and separation in work activities. Building Information Modeling (BIM) has demonstrated the potential for solving these issues. The study aims to investigate and analyze the cost-benefit analysis of using BIM compared to traditional methods in public construction projects in Iraq. Therefore, the study evaluated Multiple case studies of two projects quantitatively and conducted several interviews with 15 experts to determine the cost-benefit of adopting BIM compared to conventional methods. The study investigated the benefits of BIM in construction projects due to the remarkable difference between the two methods. The quantitative data of study findings revealed a significant cost improvement using BIM rather than the traditional method in public projects. To conclude, multi-cultural studies need to assess the projects' performance of large and small entities. Furthermore, this research suggested incorporating BIM adoption in government organizations in a wide range.
References
Alsamarraie and F. Ghazali, 2022, “Evaluation of organizational procurement performance for public construction projects : systematic review,” International Journal of Construction Management, 22(6): 1–10, doi: 10.1080/15623599.2022.2070447.
M. Abubakar, Y. Ibrahim, D. Kado, and K. Bala, 2014, “Contractors Perception of the Factors Affecting Building Information Modelling (BIM),” Computing in Civil and Building Engineering, 167–178, doi: 10.1061/9780784413616.053.
M. Alsamarraie, F. Ghazali, Z. M. Hatem, and A. Y. Flaih, 2022, “A Review on the Benefits, Barriers of The Drone Employment in the Construction Site,” Jurnal Teknologi, 84(2): 121-131 [Online]. Available: https://journals.utm.my/jurnalteknologi/article/view/17503
GÖKGÜR, A., 2015. “Current and future use of BIM in renovation projects,” Chalmers, Univ. Technol. 32,
A. Sattineni and R. H. Bradford, 2011. “Estimating with BIM: A survey of US construction companies,” Proceedings of the 28th International Symposium on Automation and Robotics in Construction, ISARC 2011, 564–569, doi: 10.22260/isarc2011/0103.
S. Azhar, 2011, “Building information modeling (BIM): Trends, benefits, risks, and challenges for the AEC industry,” Leadership and Management in Engineering, 11(3): 241–252, doi: 10.1061/(ASCE)LM.1943-5630.0000127.
Y. C. Su, Y. C. Hsieh, M. C. Lee, C. Y. Li, and Y. C. Lin, 2013. “Developing BIM-based shop drawing automated system integrated with 2D barcode in construction,” Proceedings of the 13th East Asia-Pacific Conference on Structural Engineering and Construction, EASEC 2013,
S. Zhang, J. Teizer, J. K. Lee, C. M. Eastman, and M. Venugopal, 2013 “Building Information Modeling (BIM) and Safety: Automatic Safety Checking of Construction Models and Schedules,” Automation in Construction, 29: 183–195, , doi: 10.1016/j.autcon.2012.05.006.
A. M. Abd and A. S. Khamees, 2017. “As built case studies for BIM as conflicts detection and documentation tool,” Cogent Eng., 4(1): 1411865,
C. R. C. C. Innovation, 2007. “Adopting BIM for facilities management: Solutions for managing the Sydney Opera House,” Cooperative Research Center for Construction Innovation, Brisbane, Australia.
K. din Wong and Q. Fan, 2013 “Building information modelling (BIM) for sustainable building design,” Facilities, 31(3): 138–157. doi: 10.1108/02632771311299412.
S. Fai, K. Graham, T. Duckworth, N. Wood, and R. Attar, “Building Information Modelling and Heritage Documentation,” 23rd International Symposium, International Scientific Committee for Documentation of Cultural Heritage (CIPA), 2011, [Online]. Available: http://cipa.icomos.org/text files/PRAGA/Fai.pdf
Y. Rezgui, T. Beach, and O. Rana, 2013. “A governance approach for BIM management across lifecycle and supply chains using mixed-modes of information delivery,” Journal of civil engineering and management, 19(2): 239–258.
T. G. Kekana, C. O. Aigbavboa, and W. D. Thwala, 2014 “Building Information Modelling (BIM): Barriers in Adoption and Implementation Strategies in the South Africa Construction Industry,” International Conference on Emerging Trends in Computer and Image Processing, 109–111.
M. M. Tahir, N. A. Haron, A. H. Alias, A. N. Harun, I. B. Muhammad, and D. L. Baba, 2018. “Improving Cost and Time Control in Construction Using Building Information Model (BIM): A Review.,” Pertanika Journal of Science & Technology, 26(1)
L. Van Berlo, T. Dijkmans, H. Hendriks, D. Spekkink, and W. Pel, 2012. “BIM QuickScan: benchmark of BIM performance in the Netherlands,”
D. B. Thomson and R. G. Miner, 2006. “Building Information Modeling-BIM: Contractual Risks are Changing with Technology,” Fabyanske, Westra, Hart Thomson, no. November, 4
B. Hardin and D. McCool, 2015. BIM And Construction Management: Proven Tools, Methods, And Workflows. John Wiley & Sons
M. N. Isa, S. N. M. Yusof, and S. Shaharuddin, 2018. “BIM Implementation in Malaysia: A Case Study in Department of Survey and Mapping Malaysia,” FIG Congr., 9477,
K. Wong and Q. Fan, 2013. “Building information modelling (BIM) for sustainable building design,” Facilities
S. Azhar, M. Hein, and B. Sketo, 2008, “Building information modeling (BIM): benefits, risks and challenges,” in Proceedings of the 44th ASC Annual Conference, 2–5.
S.-A. Kim, Y. Choe, M. Jang, and W. Seol, 2011 “Design process visualization system intergrating BIM data and performance-oriented design information,” in Proceedings of the 28th International Symposium on Automation and Robotics in Construction. 728–733.
A. Bhatla and F. Leite, 2012. “Integration framework of BIM with the last planner system,”
W. Lu, A. Fung, Y. Peng, C. Liang, and S. Rowlinson, 2015. “Demystifying construction project time–effort distribution curves: BIM and non-BIM comparison,” J. Manag. Eng., 31(6): 4015010,
Y. K. Cho, S. Alaskar, and T. A. Bode, 2010, “BIM-integrated sustainable material and renewable energy simulation,” in Construction Research Congress 2010: Innovation for Reshaping Construction Practice, 288–297.
J. P. Zhang and Z. Z. Hu, 2011. “BIM-and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1. Principles and methodologies,” Autom. Constr., 20(2): 155–166,
A. A. Latiffi, S. Mohd, and U. S. Rakiman, 2015, “Potential improvement of building information modeling (BIM) implementation in malaysian construction projects,” in IFIP International Conference on Product Lifecycle Management, 149–158.
S. Lavy, J. Irizarry, M. Gheisari, G. Williams, and K. Roper, 2014. “Ambient intelligence environments for accessing building information,” Facilities,
C. Woodward et al., 2010, “Mixed reality for mobile construction site visualization and communication,” in Proc. 10th International Conference on Construction Applications of Virtual Reality (CONVR2010), 4–5.
Izuchukwu, 2017. “5 reasons why firms refuse to adopt BIM,”
R. Eadie, H. Odeyinka, M. Browne, C. McKeown, and M. Yohanis, 2013. “An analysis of the drivers for adopting building information modelling,” J. Inf. Technol. Constr., 18(17): 338–352
L. Wang, 2014. “Knowledge formalization and reuse in BIM-based mechanical, electrical and plumbing design coordination in new construction projects using data mining techniques.”
R. Chahrour et al., 2021, “Cost-benefit analysis of BIM-enabled design clash detection and resolution,” Constr. Manag. Econ., 39(1): 55–72, doi: 10.1080/01446193.2020.1802768.
J. Messner et al. 2019., “BIM Project Execution Planning Guide 2.2
S. Staub-French and A. Khanzode, 2007. “3D and 4D modeling for design and construction coordination: issues and lessons learned,” Journal of information technology in construction (ITcon). 12(26): 381–407.
S. Gijezen, 2010. “Organizing 3D building information models with the help of work breakdown structures to improve the clash detection process.” University of Twente.
J. Neelamkavil and S. S. Ahamed, 2012. “The return on investment from BIM-driven projects in construction,” Institute for Research in Construction, National Research Council of Canada: Ottawa, Canada.
S.-L. Fan, C.-H. Wu, and C.-C. Hun, 2015. “Integration of cost and schedule using BIM,” Journal of Applied Science and Engineering, 18(3): 223–232.
F. Elghaish, S. Abrishami, S. Abu Samra, M. Gaterell, M. R. Hosseini, and R. Wise, 2021, “Cash flow system development framework within integrated project delivery (IPD) using BIM tools,” International Journal of Construction Management, 21(6): 555–570, doi: 10.1080/15623599.2019.1573477.
R. Ahuja, A. Sawhney, M. Jain, M. Arif, and S. Rakshit, 2020, “Factors influencing BIM adoption in emerging markets – the case of India,” International Journal of Construction Management, 20(1): 65–76. doi: 10.1080/15623599.2018.1462445.
F. Jalaei, M. Zoghi, and A. Khoshand, 2021, “Life cycle environmental impact assessment to manage and optimize construction waste using Building Information Modeling (BIM),” International Journal of Construction Management, 21(8): 784-801, doi: 10.1080/15623599.2019.1583850.
A. B. Mohammed, 2022, “Applying BIM to achieve sustainability throughout a building life cycle towards a sustainable BIM model,” International Journal of Construction Management, 22(2): 148-165, doi: 10.1080/15623599.2019.1615755.
S. Gupta, K. N. Jha, and G. Vyas, 2022, “Proposing building information modeling-based theoretical framework for construction and demolition waste management: strategies and tools,” International Journal of Construction Management, 22(12): 2345-2355, doi:10.1080/15623599.2020.1786908.
A. Porwal, M. Parsamehr, D. Szostopal, R. Ruparathna, and K. Hewage, 2020,“The integration of building information modeling (BIM) and system dynamic modeling to minimize construction waste generation from change orders,” International Journal of Construction Management, 23(1): 156-166, doi: 10.1080/15623599.2020.1854930.
P. Bosch-Sijtsema and P. Gluch, 2021 “Challenging construction project management institutions: the role and agency of BIM actors,” International Journal of Construction Management, 21(11): 1077-1087. doi: 10.1080/15623599.2019.1602585.
P. Bosch-Sijtsema, A. Isaksson, M. Lennartsson, and H. C. J. Linderoth, 2017. “Barriers and facilitators for BIM use among Swedish medium-sized contractors-‘We wait until someone tells us to use it,’” Visualization in engineering, 5(1): 1–12,
Q. He, G. Wang, L. Luo, Q. Shi, J. Xie, and X. Meng, 2017. “Mapping the managerial areas of Building Information Modeling (BIM) using scientometric analysis,” International Journal of Project Management, 35(4): 670–685,
X. Zhang, S. Azhar, A. Nadeem, and M. Khalfan, 2018. “Using Building Information Modelling to achieve Lean principles by improving efficiency of work teams,” International Journal of Construction Management, 18(4): 293–300,
M. K. Najjar, K. Figueiredo, A. C. J. Evangelista, A. W. A. Hammad, V. W. Y. Tam, and A. Haddad, 2022 “Life cycle assessment methodology integrated with BIM as a decision-making tool at early-stages of building design,” International Journal of Construction Management, 22(4): 541-555. doi: 10.1080/15623599.2019.1637098.
Y. Zou, A. Kiviniemi, and S. W. Jones, 2017. “A review of risk management through BIM and BIM-related technologies,” Safety science, 97: 88–98.
S. Kalantari, M. M. Shepley, Z. K. Rybkowski, and J. Bryant, 2017. “Designing for operational efficiency: facility managers’ perspectives on how their knowledge can be better incorporated during design,” Architectural Engineering and Design Management, 13(6): 457–478.
S. mok Paik, P. Leviakangas, and J. Choi, 2022, “Making most of BIM in design: analysis of the importance of design coordination,” International Journal of Construction Management, 22(12): 2225-2233. doi: 10.1080/15623599.2020.1774837.
P. L. Le, A. Chaabane, and T. M. Dao, 2022, “BIM contributions to construction supply chain management trends: an exploratory study in Canada,” International Journal of Construction Management, 22(1): 66-84, doi: 10.1080/15623599.2019.1639124.
L. J. Magill, N. Jafarifar, A. Watson, and T. Omotayo, 2022, “4D BIM integrated construction supply chain logistics to optimise on-site production,” International Journal of Construction Management, 22(12): 2325-2334. doi: 10.1080/15623599.2020.1786623.
A. Ahankoob, K. Manley, C. Hon, and R. Drogemuller, 2018. “The impact of building information modelling (BIM) maturity and experience on contractor absorptive capacity,” Architectural Engineering and Design Management, 14(5): 363–380,
S. Mostafa, K. P. Kim, V. W. Y. Tam, and P. Rahnamayiezekavat, 2020. “Exploring the status, benefits, barriers and opportunities of using BIM for advancing prefabrication practice,” International Journal of Construction Management, 20(2): 146–156.
L. Ferme, J. Zuo, and R. Rameezdeen, 2018. “Improving collaboration among stakeholders in green building projects: Role of early contractor involvement,” Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 10(4): 4518020.
A. Enshassi, A. Ayyash, and R. M. Choudhry, 2016. BIM for construction safety improvement in Gaza strip: awareness, applications and barriers,” International Journal of Construction Management, 16(3): 249–265, doi: 10.1080/15623599.2016.1167367.
M. M. Hossain and S. Ahmed, 2022, “Developing an automated safety checking system using BIM: a case study in the Bangladeshi construction industry,” International Journal of Construction Management, 22(7): 1206-1224. doi: 10.1080/15623599.2019.1686833.
M. Sami Ur Rehman, M. J. Thaheem, A. R. Nasir, and K. I. A. Khan, 2022 “Project schedule risk management through building information modelling,” International Journal of Construction Management, 22(8): 1489-1499. doi: 10.1080/15623599.2020.1728606.
R. Khoshfetrat, H. Sarvari, D. W. M. Chan, and M. Rakhshanifar, 2022, “Critical risk factors for implementing building information modelling (BIM): a Delphi-based survey,” International Journal of Construction Management, 22(12): 2375-2384, doi: 10.1080/15623599.2020.1788759.
H. Alzraiee, 2022, “Cost estimate system using structured query language in BIM,” International Journal of Construction Management, 22:14, 2731-2743, doi:10.1080/15623599.2020.1823061.
A. Okakpu, A. Ghaffarianhoseini, J. Tookey, J. Haar, A. Ghaffarianhoseini, and A. U. Rehman, 2022. “Risk factors that influence adoption of Building Information Modelling (BIM) for refurbishment of complex building projects: stakeholders perceptions,” International Journal of Construction Management, 22(13): 2446-2458. 1795985.
S. S. Martins, A. C. J. Evangelista, A. W. A. Hammad, V. W. Y. Tam, and A. Haddad, “Evaluation of 4D BIM tools applicability in construction planning efficiency,” International Journal of Construction Management, 22:15, 2987-3000, 2022, doi: 10.1080/15623599.2020.1837718.
M. M. Singh, A. Sawhney, and A. Borrmann, 2019, “Integrating rules of modular coordination to improve model authoring in BIM,” International Journal of Construction Management, 19(1): 15–31, doi: 10.1080/15623599.2017.1358077.
S. Mostafa, K. P. Kim, V. W. Y. Tam, and P. Rahnamayiezekavat, 2020. “Exploring the status, benefits, barriers and opportunities of using BIM for advancing prefabrication practice,” International Journal of Construction Management, 20(2): 146–156, doi: 10.1080/15623599.2018.1484555.
J. W. Creswell, 2005. “Chapter 14: Grounded theory designs,” Educational research: Planning, conducting, and evaluating quantitative and qualitative research.
J. Corbin and A. Strauss, Basics of qualitative research: Techniques and procedures for developing grounded theory. Sage publications, 2014.
J. W. Creswell and V. L. P. Clark, 2017. Designing and conducting mixed methods research. Sage publications,
Bernard, 2013.Social research methods: Qualitative and quantitative approaches. Sage.
J. W. Creswell and C. N. Poth, 2016. Qualitative inquiry and research design: Choosing among five approaches. Sage publications.
M. Oliver-Hoyo and D. Allen, 2006. “The Use of Triangulation Methods in Qualitative Educational Research.,” Journal of College Science Teaching, 35(4).
J. L. Beard, E. C. Wundram, and M. C. Loulakis, 2001. Design-build: Planning through development. McGraw-Hill Education,
M. Johansson, M. Roupé, and P. Bosch-Sijtsema, 2015. “Real-time visualization of building information models (BIM),” Automation in Construction, 54: 69–82,
D. Forgues, I. Iordanova, F. Valdivesio, and S. Staub-French, 2012. “Rethinking the cost estimating process through 5D BIM: A case study,” in Construction Research Congress 2012: Construction Challenges in a Flat World, 778–786.
J. D. Manrique, M. Al-Hussein, A. Bouferguene, and R. Nasseri, 2015. “Automated generation of shop drawings in residential construction,” Automation in Construction, 55: 15–24.
H. Moon, H. Kim, V. R. Kamat, and L. Kang, 2015. “BIM-based construction scheduling method using optimization theory for reducing activity overlaps,” Journal of Computing in Civil Engineering, 29(3): 4014048,
A. O. Akponeware and Z. A. Adamu, 2017. “Clash detection or clash avoidance? An investigation into coordination problems in 3D BIM,” Buildings, 7(3): 75,
M. Kassem, G. Kelly, N. Dawood, M. Serginson, and S. Lockley, 2015. “BIM in facilities management applications: a case study of a large university complex,” Built Environment Project and Asset Management,
H.-J. Gless, D. Hanser, and G. Halin, 2017 “BIM-agile practices experiments in architectural design,” in International Conference on Cooperative Design, Visualization and Engineering. 135–142.
J. Park and H. Cai, 2017 “WBS-based dynamic multi-dimensional BIM database for total construction as-built documentation,” Automation in Construction, 77: 15–23.