Performance Improvement of Concrete Pouring Process Based Resource Utilization Using Taguchi Method and Computer Simulation

Authors

  • Seyed Mojib Zahraee Faculty of Mechanical Engineering, Department of Industrial Engineering, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor, Malaysia
  • Ghasem Rezaei Faculty of Mechanical Engineering, Department of Industrial Engineering, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor, Malaysia
  • Ataollah Shahpanah Faculty of Mechanical Engineering, Department of Industrial Engineering, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor, Malaysia
  • Ali Chegeni Faculty of Mechanical Engineering, Department of Industrial Engineering, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor, Malaysia
  • Jafri Mohd Rohani Faculty of Mechanical Engineering, Department of Industrial Engineering, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor, Malaysia

DOI:

https://doi.org/10.11113/jt.v69.2225

Keywords:

Concrete pouring process, performance measurement, resource combination, computer simulation, Taguchi method

Abstract

One of the most controversial issues in construction management is performance measurement. Construction managers are always involved in evaluation of resource changes which effect process performance. Due to limitations and also cost of resources, resource allocation has become a complex task in construction projects. To evaluate the effects of different resources on total project performance, managers strive to allocate limited resources by determining resource combinations. This paper aims at conducting Taguchi method along with computer simulation to determine the optimum combination of resources for a real world case study involving a concrete pouring operation in order to reduce cycle time and process costs. The proposed simulation model was conducted under Arena 13.9. Final result shows that the optimum resource combination will be achieved when all of resources are located in the low level. This means that number of trucks, spreader crew, vibrator crew and finisher crew should be equal to 3, 1, 1, and 1 respectively to improve the total performance.

References

PEA. 1998. Guide to a BSC Performance Management Methodology. Procurement Executives’ Association USA.

I. Akkoyun, A. Dikbas. 2008. Performance in Construction: A Literature Review of Research in Construction Management Journals. Project Management Centre, Istanbul Technical University, Turkey,

A. Baldwin, R. McCaffer, I. OsmanI. 2001. Project Performance in a Contracting Organization: Analysis Evaluation and Development. CIB World Congress, Willington, New Zealand.

A. Nikakhtar, A. Abbasian, K. Wong. 2012. Sensitivity Analysis of Construction Processes using Computer Simulation: A Case Study. Advanced Science Letters. 13: 680–684.

E. Alkok, F. Erbatur. 1997. Productivity Improvement in Concreting Operations through Simulation Models. Building Research and Information. 25(2): 82–91.

M. Khatab, K. Soyland. 1996. Limited Resource Allocation in Construction Projects. Journal of Computer Industrial Engineering. 31(1–2): 229–232.

P. Konstantinidis. 1998, A Model to Optimize Project Resource Allocation By Construction Balanced Histogram. European Journal of Operation Research. 104(3): 559–571.

J. Fairclough. 2002. Rethinking Construction Innovation and Research: a Review of Government R and D Policies and Practices. Department of Trade and Industry, London.

R. Nicholson. 1999. Egan – Rethinking Construction, Paper Presented at the Construction Productivity Network Seminar†Royal Institution of British Architects, Birmingham, November.

J. Egan. 1998. Rethinking Construction, Report from the Construction Task Force. Department of the Environment, Transport and Regions, UK.

M. Bruni, P. Beraldi, F. Guerriero, E. Pinto. 2010. A Scheduling Methodology for Dealing with Uncertainty in Construction Projects. Engineering Computations. 28(8): 1064–1078.

S. Chen, F. Griffis, P. Chen, l. Chang. 2011. Simulation and Analytical Techniques for Construction Resource Planning and Scheduling. Automation in Construction. 21: 99–113.

H. Taghadosi, S. Abourizik. 2010. Simulation-based Scheduling of Modular Construction using Multi-agent Resource Allocation. In the proceedings of Second International Conference on Advances in System Simulation, Nice, France. 115–120.

H. Zhang, C. Tam. 2003. Fuzzy Decision-Making for Dynamic Resource Allocationâ€, Construction Management and Economics. 21(1): 31–41.

S. M. Zahraee, M. Hatami, J. M. Rohani, H. Mihanzadeh, M.R. Haghighi. 2014. Comparison of Different Scenarios using Computer Simulation to Improve Manufacturing System Productivity: a Case Study. Advance Materials Research. 845: 770–774.

A. Shahpanah, S. Poursafary , S. Shariatmadari, A. Gholamkhasi1, S. M. Zahraee،.2014. Optimization Waiting Time at Berthing Area of Port Container Terminal with Hybrid Genetic Algorithm (GA) and Artificial Neural Network (ANN) .،Advanced Materials Research.، 902،: 431–436.

T. Zayed, D. Halpin. 2001. Simulation of Concrete Batch Plant Production. Journal of Construction Engineering and Management. 12(2): 132–141.

R. Huang, J. Chenb, K. Sunb. 2004. Planning Gang Formwork Operations for Building Construction Using Simulations. Automation in Construction. 13(6): 765–779.

D. Lee, C. Yi, T. Lim, D. Arditi. 2009. Integrated Simulation System for Construction Operation and Project Schedulin. Journal of Computing in Civil Engineering. 24(6): 557–569.

A. Nikakhtar, K. Wong , M. H. Zarei, A. Memari. 2011. Comparison of Two Simulation Software Systems for Modeling a Construction Process. In the Proceedings of 2011 Third International Conference on Computational Intelligence, Modeling & Simulation, Langkawi, Malaysia. 200–205.

S. M. Zahraee, M. Hatami, N.M. Yusof, M. Rohani, F. Ziaei, 2013. Combined Use of Design of Experiment and Computer Simulation for Resources Level Determination in Concrete Pouring Process. Jurnal Teknologi. 64(1): 43–49.

K. Ahmed. 1999. Modeling Drivers' Acceleration and Land Changing Behavior, ITS Program. Massachussettes Institute of Cambridge.

C. Chan et al. 2010. Preparation and Characterization of Gasochromic Pt/WO3 Hydrogen Sensor by using the Taguchi Design Method. Sens Act B. 145: 691–7.

TN. Tsai. 2011. Improving the Fine-pitch Stencil Printing Capability Using the Taguchi Method and Taguchi Fuzzy-based Model. Robot Comput Integr Manuf. 27: 808–17.

Z. Mallick. 2010. Optimization of the Operating Parameters of a Grass Trimming Machine. Appl Ergon. 41: 260–5.

R. Kishore, R. Tiwari, I. Singh. 2009. Investigation of Drilling in [(0/90)/0]S Glass Fibre Reinforced Plastics Using Taguchi Method. Adv Prod Eng Manage. 4(1–2): 37–46.

J. Antony. 1998. Some Key Things Industrial Engineers Should Know about Experimental Design, Logistic Information Management. 11(6): 386–92.

R. Shetty, R. Pai, S. S. Rao, V. Kamath, 2008. Machinability Study on Discontinuously Reinforced Aluminium Composites (DRACs) using Response Surface Methodology and Taguchi’s Design of Experiments Under Dry Cutting Condition. Maejo International Journal of Science and Technology. 2(01): 227–239.

P. J. Ross. 1988. Taguchi Method for Quality Engineering. McGraw-Hill Publishers, New York, NY.

J. Antony, F. Antony. 2001. Teaching the Taguchi Method to Industrial Engineers. Work Study. 50(4): 141–149.

Downloads

Published

2014-06-20

Issue

Section

Science and Engineering

How to Cite

Performance Improvement of Concrete Pouring Process Based Resource Utilization Using Taguchi Method and Computer Simulation. (2014). Jurnal Teknologi, 69(1). https://doi.org/10.11113/jt.v69.2225